As architects we tend to concentrate on the design and overall vision of the project. In most cases the architect is solely responsible (as the agreement would have been signed between client and architect) and is fully accountable for any erroneous decisions, drawings or judgement calls. In large scale projects, there is no option but to engage with specialists such as HVAC, Electrical, and Acoustics etc. In case of any errors done by the sub-consultants, the architect would still be accountable.
A case in point would be one of our projects done for a very large auditorium. Over eight sub-consultants were hired by us before commencing the project. A joint meeting was held with all the consultants with the study model, plans and basic working drawings to iron out any clashes, oversights and defects in the plan. On finalization the consultants were asked to submit their detailed drawings to us along with the specifications and estimates. This was superimposed and combined and resent to all concerned to further ensure that there were no wrinkles and conflicts.
During the course of construction it was found that some of the sub-consultants had inflated the estimates and others had missed out on some key items in the specifications. Ultimately we lost fees for the devalued cost of the services as well had to pay a penalty for the delay in completion of work as well as increase in non-tendered items.
Outcome: We have now decided to retain a major portion of the consultant fees to offset any penalty incurred by us. �