One of our client was building a moderate size project. The plans were finalized and a formal tender was floated. After the agreement the contractor was awarded the work and given the clearance to start the project. Within a week when most of the excavation was completed, I got an extremely agitated call at 6:00 AM from the client. He refused to talk on the phone and insisted that I come to the site immediately.
When I reached the site, the contractor and the client were arguing loudly in the middle of the road. As soon as he saw me the client insisted that the contract be terminated immediately and contactor penalized. The reason was that he saw the poor quality of the blocks being used for the “temporary watchman / cement shed” being built by the contractor. In spite of the assurances given by the contractor that the same blocks will not be used for his project, he refused to accept it. Only after pacifying the client for over an hour did he relent on the assurance that the shed would be rebuilt with superior quality blocks.
Outcome: We now have a clause in the tender that all temporary sheds be completely removed from site after the works are over and under no circumstances are the temporary shed materials be reused in the main project.

One learns so much
You make me laugh. Why don’t you take a look at the AIA contracts and adapt them to Indian regulations? The temporary sheds that you mention are a whole another section referred to as General Conditions and Requirements which talks about and contractually binds both the owner and contractor to a number of clauses. Further, your bid documents should include a Construction Operations Plan which clearly delineates the site operations – you have buy in from both the owner/ contractor and architect. Also, the owner has no business dictating the use and non use of blocks – the means and methods of construction are the contractors and if the end result doesn’t meet the standard, the problem can be addressed. Aren’t masonry walls reviewed? Steel inspected and all other systems tested prior to occupancy?
I’m happy you got a chuckle out of this….this episode was over 20 years ago… although since then there have been a number of contractual agreements with constant improvements, you have obviously missed out on the fact that this is India. The CoA is a defunct body, the architect is not the final signatory and unlike the US we have no standardisation or adherence to the rules..all these become applicable only in large scale projects …90% of the smaller projects are done directly by the client with the help of a mason or civil engineer….we still have a way to go in terms of adherence to rules and regulations..